CASE STUDY




                                                                                         C O N T R O L   P A N EL S





        The Solution
        Coordination of a team of contractors and customising the panel design.
        Bensons’ engineering team identified specialist contractors to
        provide welding, electrical and air-conditioning expertise for
        the fit-out of the containers. Once the mechanical and electrical
        fit-out of the container was complete, its floor was modified to
        accommodate the incoming and outgoing cables.
        While coordinating the team of contractors, Bensons’
        engineering team also took the control panels designs from
        TBA, adapting them for manufacture.

        Following a carefully prepared project plan, it was possible to
        align the completion of the container fit out with the start of
        manufacture of the MCC. This meant the control panel was
        assembled and tested inside the container, minimising the
        time and cost associated with the build.
        Close co-ordination between Bensons and TBA meant the
        factory acceptance test of the completed systems could be
        undertaken immediately after Bensons’ testing of the control
        panel, with delivery to the site in Paris occurring immediately
        afterwards.
        By having a large separate and secure 370m² facility, Bensons
        was able to carry out the container fit out and panel build
        entirely undercover. This allowed the teams to avoid any
        delays caused by poor weather during winter.







        The Result
        Optimal build - rapid completion – extra projects secured

        The two initial containerised MCCs were completed and delivered
        on time and to budget.
        By achieving the aggressive project timescales, TBA and
        Bensons were successful in delivering a key element of the
        Parisian Metro extension programme. As a result of this,
        TBA won a significant tranche of work associated with the
        broader programme of work.
        This resulted in eight containerised systems and over one
        hundred ancillary panels being built and delivered between
        July 2019 and February 2020, with each milestone delivery
        being completed on time and in full.

        By working closely with our network of suppliers through-
        out this process, Bensons was able to optimise its fit out
        and build process. This made it possible to produce a
        system in an eight- week period from receipt of instruction
        to proceed.