Page 17 - Bensons Panels - Case Studies
P. 17

CASE STUDY



                                                                                         C ONTR OL  P ANELS
                                    Basingstoke
                                    Aquadrome


                                                                                        SUPPLIER:
        The Company and Project                                                         Bensons Control Panels

        Total Leisure Engineering are a long standing client of Bensons, their          CLIENT:
                                                                                        Basingstoke Aquadrome
        core business is the provision of technical support to swimming pool
        and leisure facilities across the UK, including filtration and water             PROJECT:
        treatment, air and water features, hydraulic moveable floor systems              Design and Manufacture control
        and electrical control systems                                                  panels for a major leisure pool
                                                                                        refurbishment
        In early 2022, councillors in Basingstoke agreed a major investment
        in Basingstoke Aquadrome so that it could be upgraded for future                RESULTS:
        generations to enjoy . As part of this, Total Leisure Engineering were          A substantial project delivered to
        requested to up-grade the swimming pool water filtration system for              tight timescales
        the various pools on site.







        The Challenge
        To design and manufacture the control panels quickly to deliver
        a solution within the project refurbishment timeframes.

        Since this was a refurbishment project, the plantroom on site was
        already constructed and had equipment in place. The space for
        the suite of control panels was pre-defined, meaning that
        the solution designed by Bensons needed to fit in the
        existing space. In addition, the existing plant meant that
        the 7.2m wide suite of control panels had to be designed
        such that it could be delivered in six sections of 1m and
        one section of 1.2m wide, then re-assembled on site.


















                                                             The project was carried out during 2022, when the
                                                             global supply chain was still struggling to supply
                                                             equipment in a timely manner.


                                                             This meant that Bensons had to identify a different
                                                             supplier of Variable Speed Drives to use on this
                                                             project, since our normal supplier was unable to
                                                             meet the component lead-times.